1. In a project, a project expeditor has more power and control than a person who is just a project coordinator. True or False?
Correct Answer is : FALSE
2. Which one of the following is NOT a stakeholder in a project?
Correct Answer is : None of the above
3. Which of the following is not a matrix form of organization?
Correct Answer is : Tight matrix
4. A project can have all of the below mentioned characteristics except
Correct Answer is : repeating every month
5. The float of activities in a critical path is
Correct Answer is : always zero