1. What is used to determine the recommended degree of rigor with which the software process should be applied on a project?
Correct Answer is : Adaptation criteria
2. What evaluates the risk associated with the technology to be implemented as part of project scope?
Correct Answer is : Preliminary concept planning
3. Which of the following is not an adaptation criteria for software projects?
Correct Answer is : Customers Complaints
4. Every task that is scheduled should be assigned to a specific team member is termed as
Correct Answer is : Defined responsibilities
5. What is a collection of software engineering work tasks, milestones, and deliverables that must be accomplished to complete a particular project?
Correct Answer is : Task set