1. Which process comes after batching in manufacture process?
A. Transportation
B. Placing
C. Mixing
D. Compacting
Show Correct Answer
Correct Answer is :
Mixing
2. Ready mix plant and central mix plant differ in:
A. Transportation
B. Setting time
C. Properties
D. Water addition
Show Correct Answer
Correct Answer is :
Water addition
3. How many methods of batching are there?
A. 2
B. 3
C. 5
D. 6
Show Correct Answer
Correct Answer is :
2
4. What is the maximum height through which concrete can be poured?
A. 0.1-0.6 m
B. 0.8-1 m
C. 0.5 m
D. 2 m
Show Correct Answer
Correct Answer is :
0.8-1 m
5. How many types of machine mixers are available?
A. 2
B. 5
C. 6
D. 3
Show Correct Answer
Correct Answer is :
3