Total Project Management interview questions

Total Project Management interview questions

Take as many assements as you can to improve your validate your skill rating

Total Questions: 5

1. What are the Five Project Management Process Group in order?

Correct Answer is : Initiating, Planning, Executing, Monitoring & controlling and Closing

2. Which Process Group has the highest No of Processes?

Correct Answer is : Planning & Controlling

3. You are a Project Manager currently . You have finalised the list of Stakeholders, Which Process Group you are working in

Correct Answer is : Initiating

4. Which of the following is not true about Process Group.

Correct Answer is : Process Groups are Project Phases

5. Which statement relates to definition of Planning Process?

Correct Answer is : Defines and refinesthe project objectives

Similar Interview Questions

    Search for latest jobs

    Icon
    Icon